Welcome to your Community Portal

Key

General Project
Rainwise Scheme
Water Network Improvement
Eel Protection Scheme
Every Drop Counts
NIDP Flooding Project
General Wastewater

Latest Updates

By Julie Oakley

Good afternoon All, I would firstly like to wish you all a very Happy New Year and I hope you all had a lovely Christmas, This is the first update of 2025 for the Allendale treatment works, we have had a slow start to the year due to the weather conditions but we are back on course, we have now installed and backfilled the flowmeters which is a device that measures the flow rate of water into the treatment works along with the actuated valve chambers which is a structure that houses the valves that automatically manage's the water flow. We have also finished the installation of the Rotating biological contactor 1 (RBC1) and the covers, this is used in the process of the wastewater treament.  We have made the final connections to the Rotating biological contactor 2 (RBC2) and completed the concrete slab cast which will support the compressor. I would like to once again thank you for all your co-operation and continued support, in the meantime if you have any questions or issues please feel free to leave a comment below or use the details provide to contact one of the team and er willbe happy to help. thanks again Julie

By Bethany Oakley

Good morning everyone, Happy Monday. I hope you’re all well and settling into 2025. The Team on Site have made some great progress this last month so far so I wanted to share this with you: We have powered up the new MCC on the 2nd of January, when we returned after the Christmas break and this week, we successfully turned a flow through our works meeting our programme date.   The flows now run through the new Inlet Screen, Balance Tank, Primary Settlement Tank and Syphon Chamber before being distributed on the Filter by the new distributor arms and the improvements we have made mean the works can now treat more sewage before a spill to storm occurs. The next stage for us is to convert the existing Primary Settlement Tanks into Storm Tanks to increase the Storm water storage capacity of the works. Ad you can see, this is a great start to the year for sure. If you have any questions that you’d like to ask us regarding the works, then please don’t hesitate to add a comment in the box below and a member of the Project Team will respond as soon as possible. Take care and speak soon, Bethany

By Alice Blackett

Good Morning and Happy New Year! We are progressing well with our Chemical Removal works and all major civils works are now complete. Over the next couple of months, we will be testing, commissioning and optomising the system before the dosing plant becomes fully functional. Please contact us direct if you have any questions at nwl.customer@esh.uk.com

By Sarah Jayne Parvin

Good afternoon all, Due to recent poor weather conditions including the snowmelt there has been a noticeable deterioration of the ground in our site compound and access tracks, which has also affected the condition of Mount Lane  To address this we have scheduled work for Saturday 18th January, when our team will re-stone our compound and access tracks to improve the conditions. To manage dirt on nearby roads, a full time road sweeper has been in operation. We have sourced a wheel wash system, which is expected to be delivered early next week and fully operational by the end of the week. This system will help reduce mud and dirt on roads around our compound and working areas.  Over the weekend we will also have a few operatives working within the reservoir cells. We remain focused on addressing these issues and improving conditions on site and in the surrounding areas. Thank you for bearing with us as we continue this work. Thanks 

By Rachel Rutter

Good morning Hope you are all well! As you might have noticed, we are now back on site and the team have begun installation of the temporary works to allow excavations of the valve chamber and flow meter. The reduction of stone will be complete over the next week to allow the new access track to be installed. Over the next few weeks there will be an increase in large vehicles to site while materials are delivered. As always we endeavour to keep disruption to a minimum. Please contact us direct if you have any questions at nwl.customer@esh.uk.com. Thank you have a lovely weekend! Rachel

By Rachel Rutter

7 Photos
Good morning Hope you are all well! As you might have noticed, we are now back on site, positioning and setting access covers to the shaft at Plawsworth Sewerage Treatment Works. The team are cleaning out and placing the gravel strip behind the MCC kiosk and generator. Preparation for the concrete pour has begun at Plawsworth Sewerage Treatment Works. The team are using a 14-tonne excavator to reinstate the compound area and load away the hardstanding area before reinstating commences. Access covers are being lifted into position and set into the shaft and the valve chamber ready for concrete. Please contact us direct if you have any questions at nwl.customer@esh.uk.com. Thank you have a lovely weekend! Rachel        

By Rachel Rutter

6 Photos
Good morning Hope you are all well! As you might have noticed, we are now back on site, with works continuing on the Rising Main. The last two remaining directional drilling works have been completed along with the associated Rising Main Pipework. All the Rising main Pipework across the scheme is now installed with the exception of the wash out chambers and pressure testing the system which is scheduled to commence this week. The crew have installed the overflow chamber with the extraction/removal of all the drive pit shoring. The 300-diameter overflow pipework to the existing overflow pipeline is ongoing in readiness to construct new online manhole. All the drainage and manholes have been installed up to proposed new discharge chamber with the exception of approx 15 meters of pipework. Topsoil reinstatements are being carried out. The new MCC Kiosk base has been completed with our contractor Retroflo on site to install the Kiosk, with the MCC to follow at a later date. Installation of the new wet well scaffolding is in preparation. Please contact us direct if you have any questions at nwl.customer@esh.uk.com. Thank you have a lovely weekend! Rachel

By Rachel Rutter

Good morning Hope you are all well! As you might have noticed, we are now back on site and you are likely to see a lot more of the construction team as we work through the first few months of the year. The new tank is progressing well, despite the recent cold weather. The team are transporting spoil off site, and are over coming daily challenges due to the cold/wet weather. The roads are being kept clean and maintained as the work progresses.  Please contact us direct if you have any questions at nwl.customer@esh.uk.com. Thank you have a lovely weekend! Rachel

By Bethany Oakley

Good morning, I hope you are well and are settling into 2025. Since returning from the Christmas Break, the Site Team have continued progressing well with the Project, so I thought I’d share this with you. Ammonia sample point concrete shuttering and prep work. Road reinstatement prep work. NEPS installing pipe supports. Prep for MH28 to MH25 works. Intelect continue works. Concrete slots booked for every day next week. (Weather permitting). As always, if you wanted to ask us anything, please don’t hesitate to add a comment in the box below and a member of the Project Team will respond accordingly. Take care and speak soon, Bethany

By Alice Blackett

10 Photos
Stanghow Road - Lingdale, Saltburn by the Sea Happy New Year! As you might have noticed, we are now back on site and you are likely to see a lot more of the construction team as we work through the first few months of the year. We are currently working on the Meadow and preparing for the installation of the new storm drain. We have installed safety fencing around our working area with a crossing point for the general public and dog walkers to continue to make use of the Meadow whilst works are in progress.  We have implemented a rolling road closure on Balmoral Road whilst we carry out our pipework installation. We would like to thank all residents for their cooperation. Our team are currently carrying out excavation works for the Attenuation Tank on Stanghow Road. Survey works on Stanghow Road will be carried out week commencing 20th January 2025, where 2-way traffic lights will be in place. We have also been busy carrying out survey works this week on Sandringham Road and the 2-way traffic lights will be removed today, Friday 10th January.  Further survey works will be carried out throughout January in various parts of Lingdale. 2-way traffic lights will be in place on Monday 13th January on South Stanghow Road for 3 days. There lights will then move further south on Stanghow Road on Wednesday 16th January for 2 days. We would like to thank all residents of Lingdale for their patience and understanding whilst we carry out these works. Moor Crescent/Barnard Avenue, Ludworth The team have continued to install the new pipework along Barnard Avenue within 40 metre sections to minimise disruption. Due to the cold weather the last couple of weeks, the team have experienced unforeseen delays with concrete deliveries but are positive they will remain on track. Etherley Lane, Bishop Auckland Week commencing Monday 06 January the team have begun the set up of the compound area, you may see the occasional increased deliveries bringing in materials and equipment. This week the crew have begun trial holes in order to understand ground conditions and services within the area. While work progresses on Etherley Lane, the team will be working within 2-way traffic lights.  Pithouse Lane, Leamside All drainage works and benching to manholes are now complete. The CSO screen is to be installed by the end of January when we will then start on reinstatement works. Finchale View We have connected up to the existing manhole and completed the first drain run. We are excevating ready for installation of the manifold this week and new sotrage drain runs will be installed in the upcoming weeks. Please contact us direct if you have any questions at nwl.customer@esh.uk.com. Thank you  Alice and Rachel

By Dave Eden

Afternoon All. Lets get up to speed with progress on the Great Ayton STW Storm Tank: After the repairs to the surface water main and some assistance from the farmer it looks like the worst of the localised flooding has been addressed. The access road and working area in the field immediately East/South-East of the treatment works has been completed. This involved erecting a perimeter fence to the work area, stripping the topsoil and laying geo-grid soil reinforcement and stone to create a robust access road and work area. The geo-grid soil reinforcement allowed a reduction in the thickness of the stone and so financial and environmental savings. Stone we don't use doesn't have to be produced or delivered. Following the Christmas break, our specialist sub-contractor has arrived on site to commence installation of the shaft which will act as the new Storm Water Storage Tank. We have hit the ground running and hope to have the first two rings and jacking collar in place early next week. We are also continuing a number of site investigations, from trial pits to duct surveys and ground water monitoring, to ensure we installing the most efficient solution possible. That's all for now, thanks for taking the time to read and please have a look at the attached photos. Dave Eden, Project Manager

By Bethany Oakley

Good afternoon Everyone and Happy New Year, As we start a New Year, I wanted to remind you all that we will be commencing with the setup of the Site Compound this week and this should take around 1 week to complete. We will then start with the works, as per the programme. If you have any questions or queries that you'd like to ask us, please don’t hesitate to get in touch by adding a comment in the box below and a member of the Project Team will respond accordingly. Take care, Bethany
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers