Update by Peter Greenan
Hi, My name is Peter Greenan and I am Northumbrian Water Project Manager for the Aislaby Road Rising Main Project. The project involves replacing approximately 1 mile of failing pumped main from Aislaby Road Pumping Station to Allens West, Eaglescliffe. The main carries sewage from Yarm and the majority of Eaglescliffe. We are currently confirming construction estimates and the overall projects cost will be approximately £2 million. Construction is not planned until April 2020. The route of the new main is in fields and grassed areas and crosses both Aislaby Road and the A67. We would like to let customers know what the work consists of in more detail and seek their views at the same time. We will write to customers in the near future letting them know how they can find further details of what is planned and how to provide feedback. In the meantime, if you have any queries then please feel free to post them here.