Update by Sarah Jayne Parvin
Good morning all, the project team have been together this morning discussing the progress so far. As you can see in the highway things are progressing very well, and we are currently digging down approx 1.8m to construct a man hole. Once that's complete we will then be digging back to the current manhole to lay the new pipework over the coming weeks.
Komatsu are on close down for 'Factory Fortnight' which is allowing our construction vehicles to access the workspace within their car park, where we are putting the storage pipes, without using the public car park access. We have made a decision to work over the weekend while we have this opportunity to use this for of access.
I have added some photos below for you to take a look at of our works so far.
Any question please don't hesitate to contact us.
Thanks
Sarah