Update by Becky Gartland
Good afternoon everyone and Happy New Year!
I hope you all had a lovey time celebrating over the Christmas period.
Our site team recommenced works earlier this week and are continuing with the pipework installation on Kilburn Drive. The works area will be extended across the rear of the embankment from Kilburn Drive towards Belford Street over the coming few days in order to progress with the installation of pipework.
Looking ahead into next week this area of work will continue along with operations taking place within the existing shaft to modify the structure in preparation for internal pipework to be installed within the bottom of the shaft.
As always if you have any queries regarding our work, please do not hesitate to contact me.
Thank you
Becky