Update by Christine Taylor
Good afternoon,
This week our team have continued with the installation of the drainage to the west of Kilburn Drive. Works have been carried out within the shaft to install strengthening beams to intermediate landings.
Next week, the team plan to continue the drainage as above and install pipework within existing shaft in site compound area.
Have a lovely weekend.
Christine