GENERAL PROJECT

Browns Point Sewage Pumping station, Cullercoats

Together with our partners Interserve, we plan to carry out work between 8 June 2020 until early November 2020 at Browns Point Sewage Pumping Station (SPS). The project represents a £1.2 million investment which will see an upgrade with the mechanical and electrical refurbishment of the SPS. We are working closely with Interserve our supply partner to make sure any disruption is kept to a minimum. If you are going to be directly affected by our work, our site team will let you know in advance. Typical working hours will be Monday to Friday, between 8.00am and 6.00pm. During this work there will be restricted access at the bottom of Cliff Row and the promenade by the SPS will be narrowed. We'd really like to hear from you if you have any queries so please get in touch using the 'Contact us' button at the top of the page or leave a comment below. Simon Cossar NWL Project Manager

Update by Shafqat Akbar

Hello. Interserve have had a number of successful shutdowns over the recent weeks. Today we have another planned shutdown to install some new pipework inside the pumping station.

Today we have a number of specialist sub-contractors working inside the station

Interserve have agreed the programme of works with Northumbrian Water. We are making good progress.

The site team have already started on the MEICA works. 

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers