Update by Rachel Rutter
Good afternoon,
Our site team are progressing well.
Last week they continued with the excavation and installation of the new cross connection 600 diameter Ductile Iron pipework.
Cutting operations were also carried out to the existing 800 diameter scour main in readiness for the removal of the pipe. Once the pipe is removed the team will install the proposed concrete base, thrust block and associated valves and pipework.
We have now taken delivery of the new valves for the proposed 600 diameter cross connection works.
If anyone would like to discuss our works in more detail, please feel free to contact us by commenting on this post or sending an email to nwl.customer@esh.uk.com.
I have my fingers crossed that the sun will continue to shine for the next few weeks. Enjoy!
Thank you
Rachel