The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

GENERAL PROJECT

Cone Terrace, Chester Le Street

Northumbrian Water alongside their experienced partner Esh-Stantec is planning to divert a pipe bridge in your area as part of the wider Chester Burn improvement work which is being carried out by Durham County Council.

Update by Anthony Birkett

Hi Everyone

I'm delighted to share that we've finished early on Cone Terrace! We were due to finish by the end November, but due to the dedication and hard work of the site team, we've managed to get completely off site by Friday 25 October 2019. The compound and all fencing have been removed and the grassed areas have been landscaped and seeded. We have also  reinstated and opened all roads and footpaths. 

We'd like to thank all local residents for you understaning and cooperation while we have completed this work.

I was out this afternoon delivering a letter to those close to the work - a copy of which can be viewed here.

Regards

Tony

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers