Update by John Cartwright
Morning,
Just a quick update about the closure of the Aquaduct, we have decided to put the footbridge closure back to Monday 19.02.18
We are also constructing a temporary footpath running through the working area as we will be closing the footpath on Lartington Lane while we carry out the pipe installation through the road & footpath it's self.
Again we apologies of any inconvenience and ask for everyone to be patient.
Thanks, john.