CURRENT
8°C
3 mph
View Forecast
GENERAL PROJECT

Deepdale Water Main Renewal, Barnard Castle

We will be investing £900,000 in our strategic trunk mains network. This work will help secure and maintain water supplies into the future, this work will not affect your water supplies.

Start Date

October, 2017

Estimated End Date

September, 2018

Contractor

NW, ESH, MWH

Update by David Player

Good Afternoon,
Due to the weather over the last few days increasing hazards on site and the difficulties getting to site we have not been working. Today we intend to ensure the site is safe to restart works on Monday.
We apologise for any inconvenience, we will do our best to catch the time up.  Have a good weekend.
Thank you
David

Please Login in order to comment on this update.

View all updates
Rate us

Rate us

We would love to hear your feed back on our community portal.

There was an error saving your answers. Please try again.

Saving your answers.
Please wait.

Your answers have been saved. Thankyou for giving us your feedback.

1. Do you feel that our Community Portal has helped to keep you informed about our work?

2. How likely is it that you would recommend our Community Portal to a friend or colleague?

3. How likely is it that you would recommend Northumbrian Water to a friend or colleague?

4. Do you have any suggestions to improve our Community Portal? Optional

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers