Afternoon all,
It may be the Christmas period, but works have continued apace at Deepdale.
The final connection is now in place ready to be tested and commissioned straight after the Christmas shutdown. This should represent the final major hurdle of the job. Whew!
Once the final connection is in service we can begin backfilling excavations, removing the temporary pipework over the bridge and generally bringing the area back to normal.
Like most construction contractors we stop works for the Christmas period, so our traffic lights will be removed Friday 21/12/18 at around 12:00 and won’t be returning until early in the new year. This will give all the commuters and locals a 2 to 3 week breather and I’m sure you’ll all be pleased to have a break from the disruption.
The team and I would like to take this opportunity to wish you all a Merry Christmas and a Happy New Year.
Dave Eden