Hi Everyone
I was down at site yesterday and things are moving along nicely! We are currently busy building a manhole at the Durham Road end of Wood Vue, we're hoping to be finished the work in the road by Easter, so not long now!
From Tuesday 27 March 2018 we permanently reinstate the rest of Wood Vue - this should be finished by Thursday 29 March 2018. I was out trying to inform those affected by this yesterday and left this letter.
The end is in sight!
Tony