Escomb Rising Main

Project to replace a failing pumping main from Escomb Pumping Station to Etherley Moor.

Update by Sarah Jayne Parvin

Good afternoon Everyone, I would like to provide you with an update as to what we have been up to and what we have planned up until we break up for Christmas on the 21st December.

The Open trench works south of the railway are progressing well despite the weather over the last week or so, we are approximately 25% complete on this section of our project. We have opted to directional drill (horizontal wells) the lower section of the pipe line to cause minimal disruption to the land owners, this section up to the railway will be complete by Christmas.

In the new year we will erect scaffolding under the railway footbridge to allow us access to install the new pipe under the bridge deck.

If you have any questions please dont hesitate to contact us using the 'contact us' button at the top of the page.

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers