Update by Becky Gartland
Afternoon everyone,
I hope you've all had a lovely week.
I just thought I would provide you with a quick update on how the works are going. This week the site team have been installing the initial section of pipework from the Sewage Treatment Works. From next week you will see the traffic management switch over to the opposite carriageway whilst they continue with this work.
You may have also noticed some fencing being erected around the entrance to the new pumping station on South Terrace. This is to reduce the impact of noise to the local community when works commence on Monday 21 June to install the shaft which will form the pumping station.
If you have any queries regarding the works please comment on this post and I will get back to you.
Have a lovely weekend everyone!
Thank you
Becky