Update by Becky Gartland
Good afternoon everyone,
Apologies for the delay in getting your weekly update posted!
You will see from the images attached that the concrete plug and base of the shaft have now been installed. The site team will continue to finish off pointing work on the shaft walls through to the end of this week.
With regards to the drainage installation, we are continuing to progress well and are currently up to manhole 5 of 7. The tarmac reinstatements for this second section will be carried out over the coming few days.
If you have any questions regarding these works, please do not hesitate to contact me.
Thank you
Becky