Good afternoon all,
Steve has very kindly provided me with your weekly update of how things have been progressing on site this week:
Pumping Station Works Area
- Works have continued with the installation of the Valve Chamber internal floor slab and the installation of the PCC roof slabs and today we are commencing the extraction of the shoring equipment in preparation of backfilling this work will continue into a couple of days next week
Planned works following the above is to excavate between the Pumping Station and the valve chamber and install shoring in preparation of the installation of the Ductile Iron Pipework.
Durham Road Highway Drainage Works
- We have continued with the rising main section of works from new MH07 to the Pumping station works area, Butt welding & pressure testing followed by the installation of the rising main into the trench excavation then we commenced with foam concrete backfill operations which will continue into next week by a couple of days prior to carrying out permanent tarmac reinstatements/white lines and the removal of the 2 way lights adjacent to South Terrace
Hope you all have a lovely weekend and any questions please get in touch!
Thanks
Becky