Northumbrian Water are working in your are to improve our sewer network to reduce the risk of pollution incidents in Esh Winning. The Esh Winning sewer runs in close proximity to the Priest Burn and, at times of heavy rainfall, it can present a risk of pollution to the river. The solution we identified to this includes the installation of a new pumping station in the field opposite South Terrace and a new pipeline along the main road into the sewage treatment works.

Update by Becky Gartland

Afternoon all, 

Here's an update to let you know what's been happening on site this week:

Pumping Station Works Area

  • We have continued with the excavation and installation of the PCC drainage from the manhole 11 down to manhole 8. These works will continue into next week. 
  • Temporary heras fencing has been erected, followed by a strip of top soil. Installation of new drainage has also been carried out between Manhole 11 and Manhole 12. This has taken place within the field area to the rear of Wood View Car Sales in preparation for the drainage becomes operational. 
  • Final connections have been carried out on the new Rising Main with the iron pipework entering the valve chamber and all temporary shoring has now been removed and the area backfilled. 
  • The MCC/Control panel has been installed on the new concrete slab along with the Kiosk Housing. 
  • Mechanical installation works have continued this week with the completion of all pipework and non-return valves within the pumping station and valve chamber. 
  • Electrical work within the MCC panel and Kiosk have also commenced and will continue to progress over the coming weeks. This will be followed by the installation of the pumps within the pumping station ready for when the system becomes operational. 
  • Northern Power Grid have been on site this week installing new cabling for the sites power supply. Their work was completed yesterday and the two-way traffic lights removed from South Terrace. They will be returning on Monday 29 November 2021 in order to install the electric meter. This work is expected to be completed within the same day. 
  • BT were also on site yesterday connecting the lines up to the new Kiosk ready for when everything is up and running. 

There has been a lot happening on site over this last week so if you have any queries regarding any of the above, please do not hesitate to contact me. 

Have a lovely weekend!

Thanks 

Becky 

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers