Update by Becky Gartland
Good afternoon all,
Apologies for the delay in getting last weeks update out to you. I have included details of works completed last week and this week along with images of our progress.
Pumping Station Works Area adjacent to South Terrace:
Last Week
The site team have continued with the construction of the new manhole chamber in prepreartion for turning the flows which is project to take place on Monday 31st January
Retroflo have carried out further works to complete all electrical works ready to go live.
Further joinery works have been completed in the way of timber formwork and rebar in preperation for the concrete to be poured.
Works on the access road have continued to progress.
This Week
The concrete has been poured within the timber formwork of the Pumping Station and Wet Well. The site team are currently striking the forwork and installing the spring assisted covers in preperation for drilling followed by grouting work.
Access road preperations have continued with the installation of kerb rafts along with the new kerbs which will progress into next week. This will be followed by stoning the access road ready for surfacing works to be carried out.
Following the construction of the new manhole comlpeted last week, overpumping equipment has been set up ready for the flows to be turned next week.
If you have any queries at all, please let me know.
I hope you all have a lovely weekend.
Thank you
Becky