Northumbrian Water are working in your are to improve our sewer network to reduce the risk of pollution incidents in Esh Winning. The Esh Winning sewer runs in close proximity to the Priest Burn and, at times of heavy rainfall, it can present a risk of pollution to the river. The solution we identified to this includes the installation of a new pumping station in the field opposite South Terrace and a new pipeline along the main road into the sewage treatment works.

Project updates

Update by Becky Gartland

Good afternoon all, 

It's been a little while since I last provided you with an update so wanted to pop on and get you all up to date with what's been happening on site. 

Pumping Station Works Area:

  • Last week we continued with the excavation and installation of the PCC drainage from manhole 11 towards new manhole 8 as well as partly constructing the chamber of manhole 8
  • Completion of the formwork and concrete installation works to the penetrations of the Valve Chamber and Pumping Station structures
  • Following the above, the area between the Vavle Chamber and Wet Well of the pumping station has been backfilled, shoring equipment has been removed followed by stone backfill
  • Continuation of the excavation and installation of the electrical ducting and draw pits from the Kiosk to the new Valve Chamber
  • Following the above, electrical work has continued within the new Kiosk and MCC Panel as well as cable installations through the ducting into the Valve Chamber

Throughout the remainder of this week before we break up for the Christmas Holidays we will continue with the above operations along with removing the access scaffolding using a 35T crane. Demobilisation of selected plant equipment will also take place over the course of the week. 

Any questions, please let me know. 

Thank you 

Becky 

 

 

Please Login in order to comment on this update.

Update by Becky Gartland

Good evening, 

It was lovely to catch up with some of you whilst I was on site earlier today. 

In relation to the work within the pumping station area, things are continuing to progress on from last week. 

I have now added some images to last weeks update so you can see what has been happening behind the scenes. 

Any questions please let me know. 

Have a lovely weekend

Becky 

 

 

Please Login in order to comment on this update.

Update by Becky Gartland

Afternoon all, 

Here's an update to let you know what's been happening on site this week:

Pumping Station Works Area

  • We have continued with the excavation and installation of the PCC drainage from the manhole 11 down to manhole 8. These works will continue into next week. 
  • Temporary heras fencing has been erected, followed by a strip of top soil. Installation of new drainage has also been carried out between Manhole 11 and Manhole 12. This has taken place within the field area to the rear of Wood View Car Sales in preparation for the drainage becomes operational. 
  • Final connections have been carried out on the new Rising Main with the iron pipework entering the valve chamber and all temporary shoring has now been removed and the area backfilled. 
  • The MCC/Control panel has been installed on the new concrete slab along with the Kiosk Housing. 
  • Mechanical installation works have continued this week with the completion of all pipework and non-return valves within the pumping station and valve chamber. 
  • Electrical work within the MCC panel and Kiosk have also commenced and will continue to progress over the coming weeks. This will be followed by the installation of the pumps within the pumping station ready for when the system becomes operational. 
  • Northern Power Grid have been on site this week installing new cabling for the sites power supply. Their work was completed yesterday and the two-way traffic lights removed from South Terrace. They will be returning on Monday 29 November 2021 in order to install the electric meter. This work is expected to be completed within the same day. 
  • BT were also on site yesterday connecting the lines up to the new Kiosk ready for when everything is up and running. 

There has been a lot happening on site over this last week so if you have any queries regarding any of the above, please do not hesitate to contact me. 

Have a lovely weekend!

Thanks 

Becky 

Please Login in order to comment on this update.

Update by Becky Gartland

Good evening all, 

Just a quick update to notify you all that from Monday 22 November 2021 Northern Power Grid will be accompanying us on site in order to install the new electrical connections within the Pumping Station off South Terrace. In order for these works to be carried out, there will be two-way traffic lights in operation on South Terrace for up to 2 weeks.

Any queries or concerns regarding these works please get in touch with me. 

Thanks

Becky 

 

Please Login in order to comment on this update.

Update by Becky Gartland

Good morning all, 

Steve has very kindly provided me with your weekly update on how they got on last week and what you can expect to see them working on this week. 

Pumping Station Works Area

  • Last week they continued with the installation of the pipework from the Pumping Station towards the new manhole 11. Construction of the manhole chamber itself also commenced last week. 
  • Following the secondary pressure test on the rising main, this area has now been backfiled from the roadside of South Terrace towards the Valve Chamber. The final connection will be carried out later this week. 
  • Commencement of works on the new Kiosk have taken place including, excavating and stoning up with duct penetrations in preparation for the timber formwork shuttering and concrete installation later this week. 
  • Mechanical installation works have started this week to install pipework and non-return valves within the Valve Chamber heading towards the Pumping Station/Wet Well.
  • Northern Power Grid are scheduled to commence new electrical installation works to the working area on Monday 22 November 2021 which will include two-way traffic lights being in operation on South Terrace. 

If you have any queries regarding this section of work, please let me know. 

Thank you 

Becky 

 

Please Login in order to comment on this update.

Update by Christine Taylor

Good afternoon,

I just thought I would pop on here and say thank you to the wonderful site team at Esh Winning.

This year, we at Esh Stantec decided to collect toys to donate to the Laffs4kids charity, as a friend of mine at Northumbrian Water has supported them for many years.  When the team heard what we were doing they immediately put their hands in their pocket.  This morning I went to collect the cash to go shopping for the toys.

Thank you guys, as always your generousity is very much appreciated.  I will spend your money wisely and keep you updated of our charity work.

Christine

Please Login in order to comment on this update.

Update by Becky Gartland

Good afternoon all, 

A brief update this week as works have continued within the Pumping Station works area following my last update from Monday. 

Excavations have been carried out this week to enable the install the shoring from the Pumping Station towards the new manhole chamber as well as further inlet pipework being installed which will continue into next week. 

Work continued on the installation of the Rising Main from the roadside adjacent to South Terrace to the new PCC Valve Chamber as well as welding operations in this area. 

Further core drilling operations have been carried out within the pumping station in preparation for the pipework to be installed which is due to commence from Monday 8th November. 

Have a lovely weekend!

Thanks 

Becky 

 

Please Login in order to comment on this update.

Update by Becky Gartland

Good afternoon all, 

Hope you all had a lovely weekend!

Here's your weekly update of how things have been progressing on site last week. 

Pumping Station Works Area 

Last week we have continued further ground reprofiling works, as well as the deep excavation and installation of shoring from the Pumping station towards proposed new Manhole 11, we have also installed the Ductile Iron pipework withing the Pumping station in readiness to continue this week with the remaining inlet pipework towards Manhole 11

We also continued with the excavation & installation of the Rising Main from the roadside adjacent to South Terrace towards the new PCC Valve chamber although work has been a bit slower than expected due to the weather which has not been very favorable for carrying out electro fusion welding operations

Core drilling operations have also been carried out to the PCC Valve chamber in readiness for the proposed installation of the Ductile Iron pipework which is due commence over the next couple of weeks

Durham Road Highway Drainage Works

All permanent surfacing works to the Durham Road Highway are now complete including the white lining and the half road crossing just outside the Sewage Treatment Works, this was completed last Thursday with the removal of the temporary Traffic lights Friday 29th October 2021

Any questions, please feel free to contact me to discuss further. 

Thanks 

Becky 

Please Login in order to comment on this update.

Update by Becky Gartland

Good morning, 

Apologies for the delay in getting your weekly update posted. 

 

Last week the site team have continued on both sections of works as follows:-

Pumping Station Works Area

Works have continued with the back filling operations of the PCC Valve Chamber along with the removal of the shoring equipment, we have also continued with the excavation & shoring from the Pumping Station to the Valve Chamber in preparation of the Ductile Iron Pipe work between the two structures ie the Mechanical installation.

Ground reprofiling works have been carried out in preparation for the excavation and installation of the Pumping Station inlet pipe work, which commenced yesterday by excavating towards proposed new MH11

 

Durham Road Highway Drainage Works

Last week the site team continued with the removal of the trench box shoring and installation of foamed concrete/trench backfill from new MH07 to the Rising Main 90 degree bend which transmits onto the site adjacent to South Terrace, we have also carried permanent tarmac reinstatements to the above, so hopefully we should be able to remove the 2 Way traffic lights during the course of this week once we have cleared and tidied up.

This week we plan to continue excavating the Rising Main pipe work from the highway road edge to the actual newly constructed Valve Chamber followed by a secondary full test once again back to MH07 within the Highway. 

Any questions, please let me know :)

Thanks 

Becky 

Please Login in order to comment on this update.

Update by Becky Gartland

Good afternoon all, 

Steve has very kindly provided me with your weekly update of how things have been progressing on site this week:

Pumping Station Works Area

  • Works have continued with the installation of the Valve Chamber internal floor slab and the installation of the PCC roof slabs and today we are commencing the extraction of the shoring equipment in preparation of backfilling this work will continue into a couple of days next week

Planned works following the above is to excavate between the Pumping Station and the valve chamber and install shoring in preparation of the installation of the Ductile Iron Pipework.

Durham Road Highway Drainage Works

  • We have continued with the rising main section of works from new MH07 to the Pumping station works area, Butt welding & pressure testing followed by the installation of the rising main into the trench excavation then we commenced with foam concrete backfill operations which will continue into next week by a couple of days prior to carrying out permanent tarmac reinstatements/white lines and the removal of the 2 way lights adjacent to South Terrace

Hope you all have a lovely weekend and any questions please get in touch!

Thanks 

Becky 

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers