Faceby Sewage Pumping Station

Together with our supply partner, Interserve, we plan to carry out work between Monday 7th January 2019 and Friday June 7th 2019. This essential work is part of an investment programme of over £2 million and will include the refurbishment of the Faceby sewage pumping station on Bank Lane. We would really like to hear from you so if you have any queries so please get in touch using the 'Contact us' button at the top of the page or leave a comment below. Simon Cossar NWG Project Manager

Update by Brian Hall

Hello everyone

I am sure have noticed  we are now up and running on site following the Christmas break. Thank you all for bearing with us with the vehicle traffic coming on and off site, we are trying to miminize it as much as possible with all deliveries restricted to between 10am and 4pm to avoid impact on commuters and school runs etc. Hopefully we should be sufficiently developed on site to get all our vehicles off road shortly and there will be fewer deliveries.

On site excavations have progressed well and we are now laying pipe into the field, once we have finished off the tank the main part of the work will be laying pipe into the fields.

Please get in touch if you have any questions or points you wish to raise.

Brian

 

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers