Faceby Sewage Pumping Station

Together with our supply partner, Interserve, we plan to carry out work between Monday 7th January 2019 and Friday June 7th 2019. This essential work is part of an investment programme of over £2 million and will include the refurbishment of the Faceby sewage pumping station on Bank Lane. We would really like to hear from you so if you have any queries so please get in touch using the 'Contact us' button at the top of the page or leave a comment below. Simon Cossar NWG Project Manager

Update by Brian Hall

Hello everyone

The pipeline work is now complete and Faceby is now connected to Swainby Sewage Treatment works. We are now stepping up work on site.

From Monday 8th of July to Friday 19th of July there will be temporary traffic lights on Bank Lane while we carry out work to widen the access to the site. That will enable us to get large vehicles in and out of site for necessary deliveries. We apologise in advance for any inconvenience this may cause please contact us if it is causing you any issues

best regards

Brian

 

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers