Update by Sarah Jayne Parvin
Good afternoon, our latest update in October suggested we were expecting to remain on site until the end of November and demobilise the site for approximately 6 months, with an expectation to return in late spring to complete earth works and final tidying up.
These timescales have moved, and we can confirm that we will not be demobilising prior to Christmas as we still have some works to complete which are dependent on weather conditions. Once this work has been complete, we expect to leave end of January and return 6 months after our departure to construct some earth embankments and do some final tidying up. This may take up to three months to complete and will involve a significant number of vehicle movements. We will write to you again nearer the time to give you further information about our plans.
I’d like to take this opportunity to thank you for your patience and understanding while we have been carrying out our work and would like to wish you a peaceful Christmas and New Year.
Thanks
Sarah