The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

GENERAL PROJECT
CURRENT WEATHER
7°C

Fenham

We are investing £2.2 million to improve the water supply in the west end of Newcastle.

Update by Sarah Jayne Parvin

Good afternoon, our latest update in October suggested we were expecting to remain on site until the end of November and demobilise the site for approximately 6 months, with an expectation to return in late spring to complete earth works and final tidying up.

These timescales have moved, and we can confirm that we will not be demobilising prior to Christmas as we still have some works to complete which are dependent on weather conditions. Once this work has been complete, we expect to leave end of January and return 6 months after our departure to construct some earth embankments and do some final tidying up. This may take up to three months to complete and will involve a significant number of vehicle movements. We will write to you again nearer the time to give you further information about our plans.

I’d like to take this opportunity to thank you for your patience and understanding while we have been carrying out our work and would like to wish you a peaceful Christmas and New Year.

Thanks

Sarah

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers