Afternoon,
We would like to inform you’s of the work taking place in Ferryhill Station on Chilton Lane, the work will need to be done with a road closure in place to safeguard the workforce, this closure has been agreed with Durham County Council from Wednesday 8/7 2020 until 7/8/2020, we are confident that the works will be completed within 10 days, as we appreciate the disruption the road closure will cause.
The next section of works that is planned is at Cleves Avenue, the health and safety of our teams, customers and communities is our top priority. so we’ll be using temporary traffic lights from Hemsley Close to Linden Road to keep everyone safe. These lights will move as our work progresses.
Thank you for your time, continued support and patience.
Kind regards,
Bryan Hardy