Hello everyone. In this update, I want to share the good progress our site teams have made on mechanical, civils, commissioning and steelwork operations at a number of locations on site.
We have installed the pre-lime kiosk, mixer tanks and the compressor. Our teams have substantially completed the mechanical and electrical connections to the new equipment.
We are progressing with commissioning the load cells beneath the lime silo and the mixer tanks. We have also commissioned the new compressor.
Our civils team is continuing with the civils and infrastructure work at the site perimeter.
We have fabricated the steelwork and will start to install the steelwork in the post-lime lime chamber. Our site teams are working on several fronts and are making good progress.