Hello,
The new pumping station located at Newton Park Services is now complete and operational and we are currently in the process of removing the temporary site compound and completing reinstatement work.
As you may be aware, the newly constructed footpath along St Andrews Way has suffered from settlement above the recently installed pipework. We have secured this area and investigations are ongoing into the cause of this settlement. Once concluded, we will need to return to site to complete the necessary remedial works.
We anticipate making a start on the re-construction of the footpath week commencing 29 October 2018 and expect to take up to 8 weeks to complete the work.
It will be necessary to introduce temporary traffic lights along St Andrews Way to re-construct the footpath starting with 4 way lights at the roundabout with Heighington Lane and reducing to 2 way lights as we progress towards Millennium Way.
I appreciate that you may cause further disruption for the short period while we complete this work and would like to take this opportunity to thank you for your patience and cooperation.
Please Login in order to comment on this update.