The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

GENERAL PROJECT

Great Ayton Water Booster Station

Northumbrian Water are planning to carry out work between January 2022 and March 2022 at Great Ayton Water Booster Station (WBS). The project represents a £130,000 investment which will see a mechanical and electrical refurbishment of the WBS.

Update by Simon Cossar

Morning,

 A quick update following discussions with Northern Powergrid. The upgrade required doesn’t seem to be an issue, however, before they can commit there are a few more checks they need to carry out before confirming this. There is also an issue with a third party who also needs access to the same transformer.

As you can tell things are moving forward but I don’t have any firm dates as yet, but will keep you all informed of progress and dates as thing develop.

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers