Update by Simon Cossar
Morning all,
An update on the project following further discussions with Northen Powergrid (NPG). The power issue is resolved and we have paid for the required upgrade and awaiting a date from NPG, I am awaiting an update from the booster manufacturer on when the booster will be completed. I will post a firmed up timeline once I have this information.
We are planning on meeting the residents again in May,
Have a good weekend, cheers
Simon.
Please Login in order to comment on this update.