Just a brief update this week............
- Works are progressing well with the 1st stage of the new build and will hopefully achieve the water output in the next few weeks, thankfully the 24/7 work is complete.
- The new fence will be complete by Christmas.
- A new pipeline has been placed into the culvert at Kitty's burn to assist the works in getting water quality maintains the acceptable level.