Horsley Water Treatment Works Upgrade

A £46M project to upgrade Horsey WTW has now reached a key milestone. We have selected our partners, a joint venture partnership with Doosan Enpure and Interserve Construction, to upgrade the treatment works.

Start Date

March, 2016

Estimated End Date

December, 2018

Contractor

MWH, Interserve Construction, Doosan Enpure

Update by Geoff Joyce

Hi everyone

I had some holidays over the last fortnight, hence this update covers the previous two-week period.

Backfilling operations have commenced around the Rapid Gravity Filter walls to the south end of the site. Another couple of weeks and all the good work will be hidden from view. Mechanical installation continued in the Actiflo building at the north end of the site. Cladding operations continued to the walls of the Actiflo building also.

Excavation works continued to the new Birney Hill Pumping Station at the south-east corner of the site. This part of the work is now complete and ready for blinding concrete to be placed in readiness for reinforced concrete works to commence.

See photos attached.

Enjoy!!

Geoff

Please Login in order to comment on this update.

View all updates
Rate us

Rate us

We would love to hear your feed back on our community portal.

There was an error saving your answers. Please try again.

Saving your answers.
Please wait.

Your answers have been saved. Thankyou for giving us your feedback.

1. Do you feel that our Community Portal has helped to keep you informed about our work?

2. How likely is it that you would recommend our Community Portal to a friend or colleague?

3. How likely is it that you would recommend Northumbrian Water to a friend or colleague?

4. Do you have any suggestions to improve our Community Portal? Optional