Update by Christine Taylor
Good morning,
Its holiday season, so that explains the weather???
Where has that sun disappeared to?
Dave from site, who most of you will have met, has provided me with an update.
Dave has advised they have made good progress with the tunnelling, our contract partner Active Tunnelling have completed the external shell of the shaft in Johnson Street/Yetholm Road. They have also removed most of their equipment from site. Our work is still ongoing. The team are planning to complete the shaft internal set up and then install the large concrete cover and to enable them to reinstate the road.
Have a lovely week, and we will aim to provide a further update at the end of the week.
Christine