Hi Everyone
I've received a progress update from Richard and Bobby on site and things are about to get interesting!
Over the last week or so we have been setting up our compound on the grassed area off Station Road - this has including creating an access track, temporary fencing and laying a stone base.
Next we will continue with our preparations for our pipe jacking works. Pipe Jacking is where we will drive a series of pipes through the ground from one pit to another in Harvey Combe Industrial Estate and Station Road - it basically means that we can install pipes without digging up the whole road, which can only be good!
I've attached a few picture showing what we've been up to over the last week.
Have a nice day
Tony