Update by Anthony Birkett
Hi Everyone
Bobby on site has provided me with an update on this week's progress.
Obviously, with the high winds and rain, it has been a challenging week for the lads, but we have continued to make progress laying the pipes through the Kier Depot.
Next we will start digging the excavation for the drive pit in preparation for the Pipe Jacking that we mentioned in the last update. We have also had a review of our design this week, so hope to start excavating the second drive pit off Station Road next week.
I've attached a few photos of work this week, kindly provided by Bobby
Thanks
Tony