I've had a progress update from Bobby on site.
I told you last week about the issues we were having with hard ground making it more difficult than expected to dig our manhole just off Station Road. We have now overcome these problems by using a larger hammer! Next, the joiners will come on site to start work on the Jacking Wall within the excavation.
We have also made progress on the manhole just outside the Kier Depot and have started on the piling works today for the Drive Pit there.