Update by Anthony Birkett
Hi Everyone
Bobby has provided this week's update:
Work is progressing well on the basin excavation by the Lake. Wagon activity will continue to remove the clay from site for the next 5-6 weeks via Southgate.
The Gas Diversion on Station Road is complete but the Traffic Management will stay in place for a little while longer so we can monitor progress as we pass under the Gas Main. The Pipe Line Drillers have been on site here this week, preparing for the drilling under the gas main so they will be ready to go from Monday 4 February 2019.
We are continuing to make good progress with the pipe laying as we make our way towards the park.
Enjoy your weekend
Tony