Update by Anthony Birkett
Hi Everyone
Thanks to Bobby, who has provided a further update on our progress this week.
We're working hard to get the job done and making great progress! On Station Road where we have driven The Twin Pipes under the road we have lined one of the pipes, with the other to be lined at the start of next week. We are also moving along nicely with Manholes 3 and 4.
The pipework in the park area is also moving along well as we progress from Manhole 5 to Manhole 6.
And finally work has started on the footpath and planting works within the Lakeside area.
Next week we will be making a return to the Cemetery to complete some remedial works there. We don't expect this to cause a great deal of disruption to users of the cemetery, but you may see some of our guys around for the week.
Bobby has sent over a few photographs showing what we've been up to.
Regards
Tony