Update by Anthony Birkett
Hi Everyone
Thanks again to Bobby for the information for this progress update.
We have now fully lined the twin pipes under Station Road and in the same area we continue to make progress on Manholes 3 and 4, where we are removing shoring/benching works.
The work on the drainage works within the park area is also ongoing and we are now working on manhole 6 here.
This week and next we will be continuing with the work on the footpath and fishing jetty. We will also be continuing with the planting works by the Lakeside.
I've attached a few pictures taken this week of our progress.
Have a nice weekend
Tony