Update by Steve Boyd (Project Manager)
Hi everyone,
A quick update for you, following my previous blog, this last couple of weeks we have completed the temporary access road including the tarmac installation, as well as access over the existing Letch to our temporary compound set up which is also now complete. We are currently carrying out top soil strip operations within the Farmers fields in preparation to commence the pond excavations. Photos attached.
Catch up with you next week, and have a lovely weekend.
Steve.