The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

GENERAL PROJECT

Lamesley Rising Main Replacement

To replace a failing pumping main from Lamesley Sewage Pumping Station to Birtley Sewage Treatment Works.

Update by Rachel Rutter

Good Afternoon All, 

The site team are making great progress, up to now the Trial hole work for confirmation of services in the field on the corner of Haggs Lane and Lamesley road should be complete tonight. Further investigations will be required in this area to confirm the route of the existing rising main here.

Various trial holes and investigation works are planned over the coming weeks, over the full route of the new proposed rising main, running from the pumping station by Horseworld, back to the Birtley Sewage Treatment Works. 

This is the current schedule:
•    Investigation works at Junction of Moor Mill Lane and Greenford lane, planned for 11th July.
•    Investigation works by the bus stop on Haggs Lane, planned for 25th July. 
•    Investigation works at Junction of Greenford Lane and Haggs lane, date TBC.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.

Thank you 

Rachel 

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers