Our progress for last week:

  • Traffic Mangement installed on junction of Moor Mill Lane and Greenford lane. Trial hole and investigation works completed.
  • Further trial holes completed within Birtley STW.
  • Manhole surveys within Birtley STW completed.

Update for this week:

  • Works on hold due to ecology issues for trail hole across Birtley STW access road. Methods are being revised to suit.

Planned works for next few week’s:

  • Trial holes at junction of Kibblesworth Bank and Greenford Lane for W/C 25th July.
  • Road closure of Haggs Lane between Lamesley road and Greenford Lane, for 2 weeks 1st August, for further trial hole works and site establishment.
  • Set up compound within Birtley STW, W/C 1st August.
  • Commence work area prep to North Field by LAmelsey SPS W/C 1st August.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.

Thank you 

Rachel 

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers