The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

GENERAL PROJECT

Lamesley Rising Main Replacement

To replace a failing pumping main from Lamesley Sewage Pumping Station to Birtley Sewage Treatment Works.

Update by Rachel Rutter

Good afternoon all, 

The site team are progressing well whilst enjoying the good weather. Long may it continue.

Last week:

  • Set up compound within Birtley Sewerage Treatment Works
  • Commence stockproof fencing to North field

Update for this week:

  • Installation of stockproof fencing and silt netting to North field on going, and due to be completed middle of this week
  • Commence newt protection fencing to reed bed area within Birtley Sewerage Treatment Works

Planned works for next few week’s:

  • 2 week road closure on Haggs Lane, between Lamesley Road and Greenford lane to commence on 15th August
  • Trial holes on Haggs Lane, and at junction with Greenford lane due to commence 15th August
  • Site entrance works into North Field off Haggs Lane, to commence next week, complete following week.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.

Thank you 

Rachel 

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers