Update by Rachel Rutter
Good afternoon all,
The site team are progressing well whilst enjoying the good weather. Long may it continue.
Last week:
- Set up compound within Birtley Sewerage Treatment Works
- Commence stockproof fencing to North field
Update for this week:
- Installation of stockproof fencing and silt netting to North field on going, and due to be completed middle of this week
- Commence newt protection fencing to reed bed area within Birtley Sewerage Treatment Works
Planned works for next few week’s:
- 2 week road closure on Haggs Lane, between Lamesley Road and Greenford lane to commence on 15th August
- Trial holes on Haggs Lane, and at junction with Greenford lane due to commence 15th August
- Site entrance works into North Field off Haggs Lane, to commence next week, complete following week.
Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.
Thank you
Rachel