Update by Sarah Jayne Parvin
Good afternoon all, work is progressing well on site which was helped by the exceptionally good weather we all enjoyed throughout May. We have constructed the new inlet channel which will eventually house the first new screen. We are currently constructing the new concrete press slab where the two new washpress units will be sighted. Our specialist subcontractor will commence the mechanical installation of the two washpresses and screen in mid-July. Over the next four weeks we intend to complete the civil works associated with the modifications made to the inlet including completing new drainage and constructing the remaining concrete hard standings in readiness for the installation of new steel staircases and gantries.
As always if you have any questions please feel free to leave us a comment or alternatively use the contact us function at the top of this page to email the project team direct.