Update by Sarah Jayne Parvin
Good morning all, good progress continues to be made in line with our programme and we expect to be completed by Christmas. Since my last update most of the civil works have been completed including constructing below ground pipework and concrete base slabs for the new wash water booster kiosk (pictures included below).
Our electrical subcontractor has substantially completed the field cabling to the first new screen and strain presses. Control panel modifications have started this week which will allow the electrical works to be completed for the first phase of the works.
We are aiming to commission and start the proving period for the first screen and both strain presses from the 26th October 2020. Following the proving period, we will be able to remove both the old screens and compactor and install the final new screen.
The team and I would like to thank you for your continued patience and understanding while we carry out these essential works.
Please don’t hesitate to get in touch at SarahJayne.Vickers@JNBentley.co.uk or alternatively us the contact us link at the top of this page.
Thank you.
Sarah