Hello again. In today's update, I would like to tell you about the good progress we have made at our Marden Quarry site.
Our compound is in place. We established our compound within the Northumbrian Water fenceline.
We are preparing for a mechanical shutdown. We will be carrying out works on some below ground pumps. We are progressing very well with the electrical fit-out works inside the main Northumbrian Water building.
This road is very popular with members of the public. We have set up traffic management on the access road into the site to ensure we do not inconvenience our neighbours in any way.
Our works are progressing very well. We have a number of teams on site to complete the electrical, mechanical and MEICA works.