Update by Simon Bright
Hi
Again this week everything is going to plan, we are continuing with the large manholes next to Ludlaw Avenue and laying pipes. We've also been stripping off top soil between Whitehouse Lane and the main site ready to link the access. The drainage will continue next week crossing the footpath between Ludlaw Avenue and Beach Road. For public safety we will need to close the footpath from Ludlaw Avenue to Beach Road and re-open the footpath from Whitecliff Close to maintain public access. Whitehouse Lane will remain open, however, there will be a manned crossing point for site vehicles.
Simon