Update by Anthony Birkett
Hi Everyone
In my last update I mentioned that we had come across rocky ground when trying to drill under Beach Road - as a result we had to temporarily stop the drilling and went through the process of discussing the options available to complete the job. It was a choice between continuing with the drilling under the road or digging a trench across the road which would have resulted in a road closure.
After investigating both options, it has been decided that we will continue with the drilling operation. A new drill head will be shipped in from abroad to help us break through the rock. This will be with us by the end of July so the trenchless crossing is expected to be completed by the middle of August. This isn't expected to change the completion date of overall project.
Regards
Tony