Update by Joan Tatters
Morning All
Just a quick up date.......
This week there will be a change in the visuals on site............deliveries of pipework will continue, so more vehicle movement, the mounds of soil in certain areas will also be moved. We will expecting a sub-contractor to install the cable for the site mains connection so the generator can be removed before Easter.
The treatment building is currently undertaking some radical changes, all internal and underground (they will not affect your water supply) however the external work has been conducted by open cut which has saved time on the programme.
In preparation of some planned steel work booked in for 20th May, we have decided to extend our working day a little..... 0700hrs-1830hrs starting this week so you will see us later than normal.
I hope to get some photos soon so watch this space and don't forget any questions please don't hesitate to ask.
Please Login in order to comment on this update.