Good Morning,
I understand that the electricity disruption went to plan even though rock was found at the bottom of the trench but there were no delays in the outage. As far as their site work for us went, that too went really well.
Here are a few items you may find useful:-
- The contact tank and balance tank chambers have passed the "drop" test. (they have been filled with water to monitor any weeping)
- Pumping station pump plinths have been built and concreted in
- Electrical work is continuing and the progress of the subcontractor is to programme
- Installation for the tanks on the east side of the treatment building has been limited this week
- Surface water drainage in front of the pumping station completed.
The weather hasn't been to kind to the programme of the work these passed few weeks but the team are moving on ahead.
I've included some photos for you.
Please feel free to ask away if you have any questions.