GENERAL PROJECT

Murton Flooding

Together with our supply partner, ESH-MWH, we have undertaken a detailed study of the sewer network to establish the cause of flooding in the area. We want to keep you informed about our investigations and work we are considering in the Woods Terrace area.

Start Date

July, 2017

Estimated End Date

May, 2018

Contractor

NW, ESH

Update by Christine Taylor

Hi

I thought it would be a good idea to give our customers a quick insight to what our team have come up against.

As you will all be aware the team on site have been attempting to tunnel through the ground with the new sewers.  This has been a long and difficult journey which is continuing.  We have hit challenging ground, with clay, sand and rocks.  I thought you may be interested in seeing the size of the rocks we have encountered, so I have attached a photo. 

We are still on track to open the road temporally over the Christmas Period. 

Keep watching our portal for updates.

Christine

Please Login in order to comment on this update.

View all updates
Rate us

Rate us

We would love to hear your feed back on our community portal.

There was an error saving your answers. Please try again.

Saving your answers.
Please wait.

Your answers have been saved. Thankyou for giving us your feedback.

1. Do you feel that our Community Portal has helped to keep you informed about our work?

2. How likely is it that you would recommend our Community Portal to a friend or colleague?

3. How likely is it that you would recommend Northumbrian Water to a friend or colleague?

4. Do you have any suggestions to improve our Community Portal? Optional