Update by Jane Cooper
Hello,
Civil works at New Moors is now nearing completion with the new delivery road being the last major civil milestone remaining.
Site will now be concentrating on the mechanical and electrical installations; these have begun and are approximately 50% complete. The first chemical delivery will be taken next month and commissioning will commence.