Update by Jane Cooper
Hello,
The civil works on site are now complete for all the process installations, and final minor civil works should be completed by the end of January 2025.
We are now dosing chemicals into supply with sampling and monitoring for the Environmental Agency.
There are then some additional works to complete on site which involves an old tank to be refurbished, which will complete in early 2025.